Speedspace lives up to its name in Postmasburg

After the successful completion of the prefabricated on-site construction offices at Kolomela mine, Speedspace was awarded the contract for the expansion of the construction camp to provide residential accommodation (Parkhomes) on site for a further 196 people on site.

The turnkey project was awarded on 25 January 2010, and within two-and-a-half months, Speedspace handed over 16 Speedsleep dormitory units and four Speedloo prefab portable ablution units - fully furnished, connected to services and ready for occupation.